Docsity
Docsity

Prepare for your exams
Prepare for your exams

Study with the several resources on Docsity


Earn points to download
Earn points to download

Earn points by helping other students or get them with a premium plan


Guidelines and tips
Guidelines and tips

Project Management - Advanced Project Management - Lecture Slides, Slides of Project Management

This lecture is from Advanced Project Management. Key important points are: Project Management, Network Analysis, Project Network, Concurrent Activities, House Building Project, Critical Path Method, Production Management, Probabilistic Activity Times, Project Evaluation

Typology: Slides

2012/2013

Uploaded on 01/31/2013

farooq
farooq 🇮🇳

4.3

(93)

204 documents

1 / 27

Toggle sidebar

This page cannot be seen from the preview

Don't miss anything!

bg1
Project Management
pf3
pf4
pf5
pf8
pf9
pfa
pfd
pfe
pff
pf12
pf13
pf14
pf15
pf16
pf17
pf18
pf19
pf1a
pf1b

Partial preview of the text

Download Project Management - Advanced Project Management - Lecture Slides and more Slides Project Management in PDF only on Docsity!

Project Management

Project

“A project is a series of activities

directed to accomplishment of a

desired objective.”

Plan your work first…..then

work your plan

Project Network

  • Activity-on-node (AON)
    • nodes represent activities, and arrows show precedence relationships
  • Activity-on-arrow (AOA)
    • arrows represent activities and nodes are events for points in time
  • Event
    • completion or beginning of an activity in a project

(^1 )

Branch
Node

AOA Project Network for a

House

3

2 0 1 3 1 1

Lay foundation

Design house and obtain financing

Order and receive materials

Dummy Finish work

Select carpet

Select paint

Build house

AON Network for House Building

Project

Start 1

Design house and obtain financing Order and receive materials Select paint

Select carpet

Lay foundations (^) Build house

Finish work

History

  • Developed in 1950’s
  • CPM by DuPont for chemical plants
  • PERT by U.S. Navy for Polaris missile

PERT was developed by the US Navy for the planning and control of the Polaris missile program and the emphasis was on completing the program in the shortest possible time. In addition PERT had the ability to cope with uncertain activity completion times (e.g. for a particular activity the most likely completion time is 4 weeks but it could be anywhere between 3 weeks and 8 weeks).

CPM was developed by Du Pont and the emphasis was on the trade-off between the cost of the project and its overall completion time (e.g. for certain activities it may be possible to decrease their completion times by spending more money - how does this affect the overall completion time of the project?)

PERT - Project Evaluation & Review Techniques

  • Definition: In PERT activities are shown as a network of precedence relationships using activity-on-arrow network construction - Multiple time estimates - Probabilistic activity times

USED IN : Project management - for non-repetitive jobs (research and development work), where the time and cost estimates tend to be quite uncertain. This technique uses probabilistic time estimates.

CPM/PERT

These deficiencies can be eliminated to a large extent by showing the interdependence of various activities by means of connecting arrows called network technique.

  • Overtime CPM and PERT became one technique
• ADVANTAGES:
  • Precedence relationships
  • large projects
  • more efficient

Activity Slack

Each event has two important times associated with it :
  • Earliest time , Te , which is a calendar time when a event can occur when all the predecessor events completed at the earliest possible times
  • Latest time , TL , which is the latest time the event can occur with out delaying the subsequent events and completion of project.
  • Difference between the latest time and the earliest time of an event is the slack time for that event
Positive slack : Slack is the amount of time an event can be delayed without

delaying the project completion

Critical Path

  • Is that the sequence of activities and events where there is no “slack” i.e.. Zero slack
  • Longest path through a network
  • minimum project completion time

Questions Answered by CPM & PERT

  • Completion date?
  • On Schedule?
  • Within Budget?
  • Critical Activities?
  • How can the project be finished early at the least cost?

example

Illustration of network analysis of a minor redesign of a product and its associated packaging.

The key question is: How long will it take to complete this project? Activity Number

Activity Completion Time (Weeks) 1 Redesign Product 6 2 Redesign Packaging 2 3 Order and receive components for redesigned product 3 4 Order and receive Material for redesigned packaging 2 5 Assemble Products 4 6 Makeup packaging 1 7 Package redesigned product 1 8 Test Market Redesigned Product 6 9 Revised Redesigned Product 3 10 Revised Redesigned Packaging 1 11 Present Results to the Board 1

  • "What activities must be finished before this activity can start"
  • could we complete this project in 30 weeks?
  • could we complete this project in 2 weeks?

One answer could be, if we first do activity 1, then activity 2, then activity 3, ...., then activity 10, then activity 11 and the project would then take the sum of the activity completion times, 30 weeks.

“What is the minimum possible time in which we can complete this project? “

Before starting any of the above activity, the questions asked would be

We shall see below how the network analysis diagram/picture we construct helps us to answer this question.