



















Study with the several resources on Docsity
Earn points by helping other students or get them with a premium plan
Prepare for your exams
Study with the several resources on Docsity
Earn points to download
Earn points by helping other students or get them with a premium plan
Community
Ask the community for help and clear up your study doubts
Discover the best universities in your country according to Docsity users
Free resources
Download our free guides on studying techniques, anxiety management strategies, and thesis advice from Docsity tutors
This lecture is from Advanced Project Management. Key important points are: Project Management, Network Analysis, Project Network, Concurrent Activities, House Building Project, Critical Path Method, Production Management, Probabilistic Activity Times, Project Evaluation
Typology: Slides
1 / 27
This page cannot be seen from the preview
Don't miss anything!
(^1 )
3
2 0 1 3 1 1
Lay foundation
Design house and obtain financing
Order and receive materials
Dummy Finish work
Select carpet
Select paint
Build house
AON Network for House Building
Project
Start 1
Design house and obtain financing Order and receive materials Select paint
Select carpet
Lay foundations (^) Build house
Finish work
PERT was developed by the US Navy for the planning and control of the Polaris missile program and the emphasis was on completing the program in the shortest possible time. In addition PERT had the ability to cope with uncertain activity completion times (e.g. for a particular activity the most likely completion time is 4 weeks but it could be anywhere between 3 weeks and 8 weeks).
CPM was developed by Du Pont and the emphasis was on the trade-off between the cost of the project and its overall completion time (e.g. for certain activities it may be possible to decrease their completion times by spending more money - how does this affect the overall completion time of the project?)
PERT - Project Evaluation & Review Techniques
USED IN : Project management - for non-repetitive jobs (research and development work), where the time and cost estimates tend to be quite uncertain. This technique uses probabilistic time estimates.
CPM/PERT
These deficiencies can be eliminated to a large extent by showing the interdependence of various activities by means of connecting arrows called network technique.
Activity Slack
delaying the project completion
Critical Path
Questions Answered by CPM & PERT
Illustration of network analysis of a minor redesign of a product and its associated packaging.
The key question is: How long will it take to complete this project? Activity Number
Activity Completion Time (Weeks) 1 Redesign Product 6 2 Redesign Packaging 2 3 Order and receive components for redesigned product 3 4 Order and receive Material for redesigned packaging 2 5 Assemble Products 4 6 Makeup packaging 1 7 Package redesigned product 1 8 Test Market Redesigned Product 6 9 Revised Redesigned Product 3 10 Revised Redesigned Packaging 1 11 Present Results to the Board 1
One answer could be, if we first do activity 1, then activity 2, then activity 3, ...., then activity 10, then activity 11 and the project would then take the sum of the activity completion times, 30 weeks.
“What is the minimum possible time in which we can complete this project? “
Before starting any of the above activity, the questions asked would be
We shall see below how the network analysis diagram/picture we construct helps us to answer this question.