Docsity
Docsity

Prepare for your exams
Prepare for your exams

Study with the several resources on Docsity


Earn points to download
Earn points to download

Earn points by helping other students or get them with a premium plan


Guidelines and tips
Guidelines and tips

Determining Completion Time, Critical Path, and Slack Times in PERT/CPM Network - Prof. Er, Assignments of Production and Operations Management

The necessary data for determining the completion time, critical path, and slack times for a given pert/cpm network. Students are required to solve the problem manually before checking their answers using pom. The network consists of 12 activities (a to j) with their respective times and dependencies.

Typology: Assignments

Pre 2010

Uploaded on 08/05/2009

koofers-user-t7m
koofers-user-t7m 🇺🇸

4.7

(1)

10 documents

1 / 1

Toggle sidebar

This page cannot be seen from the preview

Don't miss anything!

bg1
Names ____________________________
BA 353: ICE 7
Due on Wednesday, 10/15/08, under my office door (EBH 158).
1) Determine the completion time, critical path, and slack times for the following PERT/
CPM network. Solve by hand first; then check your answers on POM if you wish.
Act I.P. Time Slack
A -- 7 Completion Time ____________
B -- 5
C A 12 Critical Path ____________
D A 8
E A 2
F B 5
G B 9
H D 9
I E,F 6
J G,I 7
2) Same instructions as problem 1).
Act I.P. Time Slack
A -- 5 Completion Time: ___________
B -- 10
C -- 13 Critical Path: ___________
D A 9
E A 3
F D 3
G E,B 8
H C 9
I F 4
J D,G 7

Partial preview of the text

Download Determining Completion Time, Critical Path, and Slack Times in PERT/CPM Network - Prof. Er and more Assignments Production and Operations Management in PDF only on Docsity!

Names ____________________________ BA 353: ICE 7 Due on Wednesday, 10/15/08, under my office door (EBH 158). 1) Determine the completion time, critical path, and slack times for the following PERT/ CPM network. Solve by hand first; then check your answers on POM if you wish. Act I.P. Time Slack A -- 7 Completion Time ____________ B -- 5 C A 12 Critical Path ____________ D A 8 E A 2 F B 5 G B 9 H D 9 I E,F 6 J G,I 7 2) Same instructions as problem 1). Act I.P. Time Slack A -- 5 Completion Time: ___________ B -- 10 C -- 13 Critical Path: ___________ D A 9 E A 3 F D 3 G E,B 8 H C 9 I F 4 J D,G 7