Docsity
Docsity

Prepare for your exams
Prepare for your exams

Study with the several resources on Docsity


Earn points to download
Earn points to download

Earn points by helping other students or get them with a premium plan


Guidelines and tips
Guidelines and tips

PMP Sample Test Questions, Exams of Project Management

Multiple choice questions with correct answers.

Typology: Exams

2021/2022

Uploaded on 02/24/2022

dylanx
dylanx 🇺🇸

4.7

(21)

287 documents

1 / 1

Toggle sidebar

This page cannot be seen from the preview

Don't miss anything!

bg1
PMP Sample Test Questions
(correct answers are bolded)
1. An accepted deadline for a project approaches. However, the project manager
realizes only 75% percent of the work has been completed. The project manager then
issues a change request.
What should the change request authorize?
A. Additional resources using the contingency fund
B. Escalation approval to use contingency funding
C. Team overtime to meet schedule
D. Corrective action based on causes
2. The project manager develops a process improvement plan to encourage continuous
process improvement during the life of the project. Which of the following is a valid tool
or technique to assist the project manager to assure the success of the process
improvement plan?
A. Change control system
B. Process analysis
C. Benchmarking
D. Configuration management system
3. The project manager meets with the project team to review lessons learned from
previous projects. In what activity is the team involved?
A. Performance management
B. Scope identification
C. Risk identification
D. Project team status meeting

Partial preview of the text

Download PMP Sample Test Questions and more Exams Project Management in PDF only on Docsity!

PMP Sample Test Questions (correct answers are bolded)

  1. An accepted deadline for a project approaches. However, the project manager realizes only 75% percent of the work has been completed. The project manager then issues a change request.

What should the change request authorize?

A. Additional resources using the contingency fund B. Escalation approval to use contingency funding C. Team overtime to meet schedule D. Corrective action based on causes

  1. The project manager develops a process improvement plan to encourage continuous process improvement during the life of the project. Which of the following is a valid tool or technique to assist the project manager to assure the success of the process improvement plan?

A. Change control system B. Process analysis C. Benchmarking D. Configuration management system

  1. The project manager meets with the project team to review lessons learned from previous projects. In what activity is the team involved?

A. Performance management B. Scope identification C. Risk identification D. Project team status meeting