


























Study with the several resources on Docsity
Earn points by helping other students or get them with a premium plan
Prepare for your exams
Study with the several resources on Docsity
Earn points to download
Earn points by helping other students or get them with a premium plan
Community
Ask the community for help and clear up your study doubts
Discover the best universities in your country according to Docsity users
Free resources
Download our free guides on studying techniques, anxiety management strategies, and thesis advice from Docsity tutors
PJM Transmission Exam With 100% Correct Answers
Typology: Exams
1 / 34
This page cannot be seen from the preview
Don't miss anything!
During System Restoration, what is the optimal Frequency Range? - CORRECT ANSWER✔✔59.
What does eDART stand for? - CORRECT ANSWER✔✔Dispatcher Application and Reporting Tool What is eDART used for? (Electronic Disp Reporting Tool) - CORRECT ANSWER✔✔It is used for: Generation Outage Scheduling, Instantaneous Reserve Checks, Generator Reactive Capabilities and to enter and submit switching What direction do VARS flow? - CORRECT ANSWER✔✔From HIGH Voltage to LOW Voltage What direction do MW flow? - CORRECT ANSWER✔✔From HIGH Phase Angle to LOW Phase Angle Which of the following factors are NOT used in forecasting load?
Dynamic Reserves consist of: - CORRECT ANSWER✔✔Governor Reserve and Load that has been restored with under frequency relays What would be the appropriate response to receiving a DC ground Alarm? - CORRECT ANSWER✔✔Advise substation personnel of the alarm during normal hours An islanded system has a load of 3000 MW. To increase frequency by 1 Hz, how much load should be shed? - CORRECT ANSWER✔✔180 MW Which of the following actions would be used FIRST to control a reactive transfer limit violation? a) Place reactors in service b) Load offcost (out of merit) generation c) Issue load dump warning d) Modify firm transaction schedules - CORRECT ANSWER✔✔B When available primary reserve capacity on a system is less than the largest operating generator, or the loss of a transmission facility jeopardizes reliable operations, PJM should issue a: a) Manual load dump warning b) Maximum emergency generation c) Voltage reduction warning d) Primary reserve alert - CORRECT ANSWER✔✔A Increased load on a circuit causes lower voltage at the remote end. Which of the following will increase this voltage?
d) 1000 MW - CORRECT ANSWER✔✔C Distribution factors are used to determine: a) The distribution of voltage levels on key lines b) The surge impedance loading of lines c) The impact of placing capacitor banks in or out of service d) How the flow of MW on a line will be redistributed upon its loss - CORRECT ANSWER✔✔D PJM has issued a heavy load voltage schedule. Which of the following is NOT an appropriate PJM member action in response to this alert? a) Ensure that all unit voltage regulators are in service b) Ensure that all unit voltage regulators are in manual mode c) Ensure that all reactors are out of service and available capacitors are in service d) Ensure that all units connected to the 500 kV system are operated so that reasonable MVAR reserve is maintained - CORRECT ANSWER✔✔B Which of the following reasons describes why opening a pre-studied EHV line has a positive effect in reducing system voltages?
During system restoration, an island requires 400 MW of dynamic reserve. The maximum load allowed with underfrequency relay protection enabled that can be counted as dynamic reserve is: a) 100 MW b) 200 MW c) 300 MW d) 400 MW - CORRECT ANSWER✔✔B What is the surge impedance loading on a typical 500 kV line? a) 230 MW b) 500 MW c) 750 MW d) 850 MW - CORRECT ANSWER✔✔D During system restoration, frequency has decayed for an islanded system to 59.05 Hz and is decaying rapidly. The operator should: a) Notify PJM and seek advice b) Call on additional generation c) Wait for the system to settle out d) Immediately shed load to recover the frequency - CORRECT ANSWER✔✔D If inclement weather postpones the start of a planned outage, the outage will: a) Be postponed indefinitely b) Be rescheduled as unplanned
When ordered, a 5% voltage reduction should be taken on: a) The 230 kV system b) The 500 kV system c) The distribution system d) Predetermined tie lines - CORRECT ANSWER✔✔C During initial transmission system restoration, shunt capacitor banks are removed from service to prevent which of the following? a) High loads b) Low voltage c) High voltage d) Low loads - CORRECT ANSWER✔✔C If a member detects or suspects actual or attempted sabotage on the bulk power system, they should
To avoid cancellation, transmission outages that are less than 5 days in length and may result in congestion should be submitted to PJM: a) 7 days prior to the outage b) 30 working days prior to the outage c) Before the first day of the week prior to the outage d) Before the first day of the month prior to the outage - CORRECT ANSWER✔✔D Two Transmission Owners (TOs) interconnect during a system restoration. TO A has restored 600 MW of load. TO B has restored 2000 MW of load. Following the interconnection, which of the following statements is true? a) TO A and TO B both control frequency b) TO A and TO B both control tie line flow c) Both TOs control frequency and tie line flow d) One TO controls tie line flow and the other TO controls frequency - CORRECT ANSWER✔✔D Which of the following are monitored during system restoration?
a) Across the entire RTO on a load-ratio share basis b) Only in control zone(s) with a deficient energy position c) Only in the Mid-atlantic region d) Only where it will be effective to unload the transmission line - CORRECT ANSWER✔✔B During system restoration, one means of keeping frequency above 59.5 Hz is to activate which of the following? a) Synchronized reserves b) Dynamic reserves c) Secondary reserves d) Shared reserves - CORRECT ANSWER✔✔A During system restoration, one means of strengthening and stabilizing an interconnected area is: a) Closing additional tie lines b) Implementing additional transactions c) Implementing emergency procedures d) Loading maximum emergency generation - CORRECT ANSWER✔✔A In cases where a data point ID fails for an extended period of time, the system operator will manually update the value: a) Every 15 minutes b) Every 30 minutes
c) Every hour d) Every 4 hours - CORRECT ANSWER✔✔B For the System shown below, if Line D were to be removed from service what would the new flow be on Line B? a) 200 MW b) 340 MW c) 560 MW d) 600 MW - CORRECT ANSWER✔✔B Will higher ambient temperatures raise or lower the ratings of equipment on the BES? Why? - CORRECT ANSWER✔✔Lower ratings because of less ability to dissipate heat When severe weather is expected, PJM may take all actions EXCEPT: A) Request reclosing to be put into service B) Defer maintenance to critical BES facilities C) Initiate conservative operations D) Shedding load - CORRECT ANSWER✔✔D What instability is characterized by continued oscillations over a long period of time? A) Oscillating B) Transient C) Dynamic
True or False: Reactive resources 230kV and below can be switched without PJM notification - CORRECT ANSWER✔✔False: 138 kV and below A generator just completed its Reactive Capability test and has recorded its reactive capability data. What should it do now?