NERC Transmission Exam | Actual Questions and Answers Latest Updated 2025/2026 (Graded A+), Exams of Electrical and Electronics Engineering

NERC Transmission Practice Test-Sample question to help prepare for the NERC Transmission Exam | Actual Questions and Answers Latest Updated 2025/2026 (Graded A+)

Typology: Exams

2024/2025

Available from 06/29/2025

WINGS_TO-FLY
WINGS_TO-FLY 🇺🇸

1

(1)

1.1K documents

1 / 2

Toggle sidebar

This page cannot be seen from the preview

Don't miss anything!

bg1
NERC Transmission Practice Test-Sample question to help prepare for the
NERC Transmission Exam | Actual Questions and Answers Latest Updated
2025/2026 (Graded A+)
Which type of relay operates on the premise of comparing the flow in and out of the area of protection?
- ✔✔Differential relay
Underfrequency load shedding is set-up so that which of the following does NOT occur? -
✔✔Uncontrolled separation
Who is responsible to make sure that the operation of voltage control equipment is coordinated with
other impacted entities? - ✔✔Transmission Operator
The coordination of voltage schedules by system operators would be utilized to reduce all of the
following EXCEPT - ✔✔Reactive inadvertent
What should a system operator expect to see if the generator increases its excitation? - ✔✔An increase
in MVAR output
A transmission line between Bus A and Bus B has MW flow from Bus B to Bus A. After the tripping of a
parallel line, the line flow from Bus B to Bus A exceeds the lines thermal rating. Which of the following
actions would assist the operator in correcting the problem? - ✔✔Increase generation at Bus A
What is a major concern for a System Operator during emergency conditions? - ✔✔System remains
connected to the Interconnection
If your system has lost a large amount of customer load due to a system disturbance, but has remained
connected to all of your neighbors, what is the best solution to consider? - ✔✔Coordinate with the
neighbors
You report for work on a peak summer day with expected high temperatures and load. What can you do
to maintain an adequate system voltage profile? - ✔✔Get under the voltage by placing capacitors in
service while maintaining operating limits
pf2

Partial preview of the text

Download NERC Transmission Exam | Actual Questions and Answers Latest Updated 2025/2026 (Graded A+) and more Exams Electrical and Electronics Engineering in PDF only on Docsity!

NERC Transmission Practice Test-Sample question to help prepare for the

NERC Transmission Exam | Actual Questions and Answers Latest Updated

2025 /202 6 (Graded A+)

Which type of relay operates on the premise of comparing the flow in and out of the area of protection?

  • ✔✔Differential relay Underfrequency load shedding is set-up so that which of the following does NOT occur? - ✔✔Uncontrolled separation Who is responsible to make sure that the operation of voltage control equipment is coordinated with other impacted entities? - ✔✔Transmission Operator The coordination of voltage schedules by system operators would be utilized to reduce all of the following EXCEPT - ✔✔Reactive inadvertent What should a system operator expect to see if the generator increases its excitation? - ✔✔An increase in MVAR output A transmission line between Bus A and Bus B has MW flow from Bus B to Bus A. After the tripping of a parallel line, the line flow from Bus B to Bus A exceeds the lines thermal rating. Which of the following actions would assist the operator in correcting the problem? - ✔✔Increase generation at Bus A What is a major concern for a System Operator during emergency conditions? - ✔✔System remains connected to the Interconnection If your system has lost a large amount of customer load due to a system disturbance, but has remained connected to all of your neighbors, what is the best solution to consider? - ✔✔Coordinate with the neighbors You report for work on a peak summer day with expected high temperatures and load. What can you do to maintain an adequate system voltage profile? - ✔✔Get under the voltage by placing capacitors in service while maintaining operating limits

If a Balancing Authority is unable to calculate ACE for more than minutes it shall notify its Reliability Coordinator. - ✔✔ 30 Your system configuration presents you with a situation of having two parallel lines between two stations. The lines have different ratings. Line A has a rating of 250 MVA, while line B has a rating of 200 MVA. Based on the line ratings, what is the first contingency transfer capability between the two stations? - ✔✔200 MVA