CSCI 3350 Homework 2: Scheduling Project Activities and Milestones - Prof. Vernon W. Pine, Assignments of Software Engineering

Details of a scheduling project for csci 3350, including task names, durations, dependencies, project milestones, and deliverables. Students are required to create a gantt chart, a network chart, and answer related questions.

Typology: Assignments

Pre 2010

Uploaded on 08/19/2009

koofers-user-x7l-1
koofers-user-x7l-1 🇺🇸

10 documents

1 / 1

Toggle sidebar

This page cannot be seen from the preview

Don't miss anything!

bg1
CSCI 3350 - Homework 2
Scheduling
(21 Points)
Project Activities
Activity
Name
Duration
(weeks)
Depends Upon
Task
1Task 1 2 None
2Task 2 2 1
3Task 3 1 1
4Task 4 1 2
5Task 5 2 2
6Task 6 5 3
7Task 7 4 3
8Task 8 2 4
9Task 9 1 5, 6
10 Task 10 1 9
11 Task 11 4 4
12 Task 12 2 7, 8, 10, 11
Project Milestones and Deliverables
Deliverable/Milestone Due Date
1Project Start Date 1 March 2009
2Draft Document 1 1 week after the end of Task 1
3Final Document 1 1 week after Deliverable 1
4Interface Prototype Completion of Task 5
5Document 2 1 week before the start of Task 4
6Document 3 1 week after the end of Task 8
7System Delivery Beginning of Task 12
Homework Problems
1. Using the above data, create a Gantt chart. Display the detailed Gantt chart that shows the
critical path. Size the chart to fit on one page. (10 points)
a. Print a copy of the Gantt chart. Ensure that the critical path is clearly marked.
2. Display a copy of the Network chart. Size the chart to fit on one page. (5 points)
a. Print the Network chart.
3. Suppose that the duration of Task 2 increase from 2 weeks to 3 weeks. What effect does this
have on the project? (2 points)
4. Reset the duration of Task 2 to 2 weeks. Now suppose the duration of Task 7 decreases from
4 weeks to 3 weeks. What effect does this have on the project? (2 points)
5. One of your team leaders has given you the follow estimates for the completion of a task:
The shortest likely time to complete the task - 6 weeks
The most likely time to complete the task - 7 weeks
The longest likely time to complete the task - 20 weeks
Calculate the task duration using the PERT technique.
(This question is not related to questions 1- 4) (2 points)
Submit hardcopies of the Gantt chart, the Network chart, and the answers to questions 3 - 5.
/app/work/qkdc4x-478756-2673278-homework-202-20-20scheduling-doc.doc

Partial preview of the text

Download CSCI 3350 Homework 2: Scheduling Project Activities and Milestones - Prof. Vernon W. Pine and more Assignments Software Engineering in PDF only on Docsity!

CSCI 3350 - Homework 2

Scheduling

(21 Points)

Project Activities

Activity Name Duration (weeks) Depends Upon Task 1 Task 1 2 None 2 Task 2 2 1 3 Task 3 1 1 4 Task 4 1 2 5 Task 5 2 2 6 Task 6 5 3 7 Task 7 4 3 8 Task 8 2 4 9 Task 9 1 5, 6 10 Task 10 1 9 11 Task 11 4 4 12 Task 12 2 7, 8, 10, 11

Project Milestones and Deliverables

Deliverable/Milestone Due Date 1 Project Start Date 1 March 2009 2 Draft Document 1 1 week after the end of Task 1 3 Final Document 1 1 week after Deliverable 1 4 Interface Prototype Completion of Task 5 5 Document 2 1 week before the start of Task 4 6 Document 3 1 week after the end of Task 8 7 System Delivery Beginning of Task 12

Homework Problems

1. Using the above data, create a Gantt chart. Display the detailed Gantt chart that shows the

critical path. Size the chart to fit on one page. (10 points)

a. Print a copy of the Gantt chart. Ensure that the critical path is clearly marked.

2. Display a copy of the Network chart. Size the chart to fit on one page. (5 points)

a. Print the Network chart.

3. Suppose that the duration of Task 2 increase from 2 weeks to 3 weeks. What effect does this

have on the project? (2 points)

4. Reset the duration of Task 2 to 2 weeks. Now suppose the duration of Task 7 decreases from

4 weeks to 3 weeks. What effect does this have on the project? (2 points)

5. One of your team leaders has given you the follow estimates for the completion of a task:

The shortest likely time to complete the task - 6 weeks

The most likely time to complete the task - 7 weeks

The longest likely time to complete the task - 20 weeks

Calculate the task duration using the PERT technique.

(This question is not related to questions 1- 4) (2 points)

Submit hardcopies of the Gantt chart, the Network chart, and the answers to questions 3 - 5. /app/work/qkdc4x-478756-2673278-homework-202-20-20scheduling-doc.doc