CQM Module 5 Questions and Answers: Understanding Submittals and Variations, Exams of Quality Management

A brief overview of submittals and variations in the context of cqm (construction quality management). It presents a series of questions and answers related to the purpose, process, and responsibilities associated with submittals and variations in construction projects. The document highlights the importance of submittals in ensuring compliance with contract specifications and the timely flow of materials. It also outlines the responsibilities of both contractors and government entities in the submittal process.

Typology: Exams

2024/2025

Available from 01/06/2025

tizian-kylan
tizian-kylan 🇺🇸

2.7

(21)

3.8K documents

1 / 2

Toggle sidebar

This page cannot be seen from the preview

Don't miss anything!

bg1
CQM Module 5 Questions and Answers
Graded A+
What is the purpose of submittals? ✔✔submittals are required by the contact to regualte the
timely flow of materials to be incorporated into work. they are necessary to demonstrate that the
propsed material etc. are in compliance with the contract
What is the process that contractor must use to request a variation? ✔✔....
What are the contractors submittal responsibilities? ✔✔integrate submittals into QC plan who
and how it be done.
Submital register accurate and up to date
work doesting begin until submittals are accepted
What are the governments submittal responsibilities? ✔✔review atleast 10% of FIO submittals
review and approve submittals that require GA
pf2

Partial preview of the text

Download CQM Module 5 Questions and Answers: Understanding Submittals and Variations and more Exams Quality Management in PDF only on Docsity!

CQM Module 5 Questions and Answers

Graded A+

What is the purpose of submittals? ✔✔submittals are required by the contact to regualte the timely flow of materials to be incorporated into work. they are necessary to demonstrate that the propsed material etc. are in compliance with the contract

What is the process that contractor must use to request a variation? ✔✔....

What are the contractors submittal responsibilities? ✔✔integrate submittals into QC plan who and how it be done.

Submital register accurate and up to date

work doesting begin until submittals are accepted

What are the governments submittal responsibilities? ✔✔review atleast 10% of FIO submittals

review and approve submittals that require GA

What information must the contractor provide in his submittal control document (ENG form 4288R- Submittal Register)? ✔✔NAS activity code

Item #

Dates in schedule column