CORAL GABLES SENIOR HIGH
SCHOOL
October 11, 2019
Overview
- As part of the GOB program, $11.2 M was originally allocated to Coral Gables Senior High School for facility renovations
- The scope of the renovations included window replacement in the original 1950s buildings, HVAC, plumbing and electrical improvements, miscellaneous renovations, security system improvements and painting
- M.C. Harry and Associates, Inc and OHL Building, Inc. were commissioned for the renovation project by the Board in February 2017
- Having determined to prioritize the partial replacement of the campus and the major infrastructure of the 1950 facility, the Board commissioned Silva Architects in May 2018 for site adaption of a 2-story classroom building completed in August 2018 at Dr. Michael Krop SHS
- The School Board increased project funding to $26.2 M in Sept 2018 to include new construction to replace the chiller plant, electrical service and buildings # and #
- To further ensure the extent of renovation to the existing facility, the School Board in Sept 2019 approved an additional $3.5 M for a total of $29.7 M funding in the Five Year Work Plan
Dr. Michael Krop SHS – Walk-thru
Groundbreaking Event
Action Plan – Phase I
- A three-phased approach was developed to prioritize the
work and to properly plan and fund the new construction
and renovation phases
- The first phase of this three-pronged action plan consist of
improvements aimed at stabilizing critical building systems
and enhancing the physical environment
- Examples of these improvements, carried out primarily by in-
house forces and substantially completed, include selected
plumbing repairs, selected roofing, exterior painting, interior
enhancements in areas of high traffic and relocation of
instructional spaces to be demolished
Action Plan – Phase I
Before
After
Action Plan – Phase I
Before
After
Action Plan – Phase I
Action Plan – Phase II
- The second phase, funded from the current GOB
allocation, was proposed to include:
- A new two-story classroom building to replace buildings
#6 and
- A new chiller plant, electrical vault and generator that will
replace the current systems and sized with capacity to
accommodate not only the new building but also the
remaining buildings on the campus
- Construction was awarded to VPI Construction in June
2019 and is underway
Action Plan – Phase II
Existing – Chiller Plant & Cafeteria
Action Plan – Phase II
Existing – Cafeteria (Riviera Drive)
Action Plan – Phase II
Existing Condition New Construction
Action Plan – Phase II
Scope of work includes:
- New 2-story 36,400 square foot classroom building consisting of; o 347 new student stations o New Dining and Kitchen, o Exterior Dining Shade Structure, o Gymnastics/Dance Room o Art Suite o Five (5) new Computer Labs o JROTC Suite o Drafting and Design Lab o Science Classroom o Three (3) Social Studies Classrooms.
- New 1-story 3,600 square foot Chiller Plant
- New PE Multi-Purpose Room and Laundry
- New Covered Walkways
- New Interior Courtyard
Action Plan – Phase II
New Chiller Plant and Electrical Vault
Action Plan – Phase II
New two-story classroom building